TY - RPRT TI - Review Report 2004: The Danish Offshore Wind Farm Demonstration Project: Horns Rev and Nysted Offshore Wind Farms Environmental Impact Assessment and Monitoring AU - Boesen, C AU - Kjær, J AB - The summary of the environmental impact assessment report (EIA) has been compiled by the two builders, Elsam and Eltra. It consists of a description of the concrete project proposal and an evaluation of the environmental consequences of installing an offshore wind farm comprised of as many as 80 wind turbines with a total output of approx. 160 MW off the point of Blåvands Huk, west of Denmark. Elsam is the builder, responsible for the offshore wind park, and Eltra is the builder in charge of the sub-marine cables and substation. DA - 2005/10// PY - 2005 SP - 135 PB - ELSAM Engineering SN - DK-2450 LA - English KW - Wind Energy KW - Fixed Offshore Wind KW - Human Dimensions KW - Environmental Impact Assessment ER -